Reddy Update: Difference between revisions
From IntRoLab
| Line 6: | Line 6: | ||
| | | | ||
* Ordered new coupling for shoulder | * Ordered new coupling for shoulder | ||
* Fab. head mechanism for gravity assist | * Fab. head mechanism for gravity assist (previous one had interference problems with other head parts) | ||
* Assembly of 1 motor PCB | * Assembly of 1 motor PCB for neck | ||
* Final tuning of motor controllers | |||
* Documentation (protocol) | |||
|- | |- | ||
| Week 32, August 3 - August 9 | | Week 32, August 3 - August 9 | ||
| | | | ||
* | * Final tests | ||
|} | |} | ||
Revision as of 13:00, 28 July 2009
Schedule
| Week 31, July 27 - August 1 |
|
| Week 32, August 3 - August 9 |
|
Head Improvements
Motor Improvements
Tuning the motor controller
RS-232 protocol enhancements
CAN command added
Future Improvements
- Single 12V power supply could be useful for direct connection to Pioneer robots. A 12V-->8.5V DC-DC (100W) converter is required for this operation. This item can be ordered at Vicor. 8.5V batteries would then be useless.