| Week 31, July 27 - August 1
|''' Week 31, July 27 - August 1'''
|  
|  
* Ordered new coupling for shoulder
* Ordered new coupling for shoulder
Line 12: Line 12:
* Documentation (protocol)
* Documentation (protocol)
|-
|-
| Week 32, August 3 - August 9  
| '''Week 32, August 3 - August 9'''
|  
|  
* Final tests & tuning
* Final tests & tuning

Revision as of 13:02, 28 July 2009

Schedule

Week 31, July 27 - August 1
  • Ordered new coupling for shoulder
  • Fab. + installation of head mechanism for gravity assist (previous one had interference problems with other head parts)
  • Assembly and installation of 1 motor PCB for neck
  • Assembly and installation of the speaker PCB + support
  • Final tuning of motor controllers
  • Documentation (protocol)
Week 32, August 3 - August 9
  • Final tests & tuning

Head Improvements

Motor Improvements

Tuning the motor controller

RS-232 protocol enhancements

CAN command added

Future Improvements

  • Single 12V power supply could be useful for direct connection to Pioneer robots. A 12V-->8.5V DC-DC (100W) converter is required for this operation. This item can be ordered at Vicor. 8.5V batteries would then be useless.

Additional Notes

Documents