* Ordered new coupling for shoulder
 
* Ordered new coupling for shoulder
* Fab. head mechanism for gravity assist
+
* Fab. head mechanism for gravity assist (previous one had interference problems with other head parts)
* Assembly of 1 motor PCB,
+
* Assembly of 1 motor PCB for neck
 +
* Final tuning of motor controllers
 +
* Documentation (protocol)
 
|-
 
|-
 
| Week 32, August 3 - August 9  
 
| Week 32, August 3 - August 9  
 
|  
 
|  
*
+
* Final tests
*
 
*
 
 
|}
 
|}
  

Revision as of 13:00, 28 July 2009

Schedule

Week 31, July 27 - August 1
  • Ordered new coupling for shoulder
  • Fab. head mechanism for gravity assist (previous one had interference problems with other head parts)
  • Assembly of 1 motor PCB for neck
  • Final tuning of motor controllers
  • Documentation (protocol)
Week 32, August 3 - August 9
  • Final tests

Head Improvements

Motor Improvements

Tuning the motor controller

RS-232 protocol enhancements

CAN command added

Future Improvements

  • Single 12V power supply could be useful for direct connection to Pioneer robots. A 12V-->8.5V DC-DC (100W) converter is required for this operation. This item can be ordered at Vicor. 8.5V batteries would then be useless.