| Week 32, August 3 - August 9  
 
| Week 32, August 3 - August 9  
 
|  
 
|  
* Final tests
+
* Final tests & tuning
 
|}
 
|}
  

Revision as of 13:01, 28 July 2009

Schedule

Week 31, July 27 - August 1
  • Ordered new coupling for shoulder
  • Fab. + installation of head mechanism for gravity assist (previous one had interference problems with other head parts)
  • Assembly and installation of 1 motor PCB for neck
  • Assembly and installation of the speaker PCB + support
  • Final tuning of motor controllers
  • Documentation (protocol)
Week 32, August 3 - August 9
  • Final tests & tuning

Head Improvements

Motor Improvements

Tuning the motor controller

RS-232 protocol enhancements

CAN command added

Future Improvements

  • Single 12V power supply could be useful for direct connection to Pioneer robots. A 12V-->8.5V DC-DC (100W) converter is required for this operation. This item can be ordered at Vicor. 8.5V batteries would then be useless.

Additional Notes