From IntRoLab
(→Schedule) |
(→Schedule) |
||
Line 3: | Line 3: | ||
{| | {| | ||
|- | |- | ||
− | | Week 31, July 27 - August 1 | + | |''' Week 31, July 27 - August 1''' |
| | | | ||
* Ordered new coupling for shoulder | * Ordered new coupling for shoulder | ||
Line 12: | Line 12: | ||
* Documentation (protocol) | * Documentation (protocol) | ||
|- | |- | ||
− | | Week 32, August 3 - August 9 | + | | '''Week 32, August 3 - August 9''' |
| | | | ||
* Final tests & tuning | * Final tests & tuning |
Revision as of 13:02, 28 July 2009
Contents
Schedule
Week 31, July 27 - August 1 |
|
Week 32, August 3 - August 9 |
|
Head Improvements
Motor Improvements
Tuning the motor controller
RS-232 protocol enhancements
CAN command added
Future Improvements
- Single 12V power supply could be useful for direct connection to Pioneer robots. A 12V-->8.5V DC-DC (100W) converter is required for this operation. This item can be ordered at Vicor. 8.5V batteries would then be useless.